3G Pitch, Changing Rooms and Wilts FA Base all Taking Shape

Work is progressing well down at Green Lane. The building is really taking shape with the contractors hoping to have the roof fitted next week.

While the building has been going up the 3G contractors have also been busy, they have been held up by the bad weather in October but now have cut and filled in the pitch area.

Hopefully they are going to be laying the tarmac in the next two weeks. The 3G perimeter fencing is also going up, as can see by the images.

For further images take a look at the Green Lane photo Album.

Wilts FA are still hopeful that all will be finished by the end of Spring 2020.